Progress To Date
A project of this size and complexity required a large amount of planning before on-site construction began in April 2009.
What’s Happened
-
consultation with former TransAdelaide (TA) - now known as Public Transport Services
-
preferred sites for new facilities identified
-
site survey and geotechnical investigations undertaken
-
detailed design of new depot
-
managing Contractor (Baulderstone Pty Ltd) appointed late 2008
-
project gained Development Approval in December 2008.
Construction commenced in April 2009 and included:
-
civil earthworks
-
installation of stormwater
-
installation of services infrastructure
-
installation of plant for train wash building
-
laying of track
-
building structures.
-
construction of buildings and other depot facilities
-
installation of 3.5 kilometre perimeter fence
-
fit-out of buildings
-
installation of signalling
-
connection to the Gawler main line.
Photographic Timeline
9 October 2009
13 November 2009
14 December 2009
11 February 2010
29 March 2010
22 April 2010
May 2010
2 July 2010
5 August 2010
7 October 2010
February 2011