Skip to main content

Sturt Highway Corridor Upgrade

The Australian and South Australian governments have committed $87.5 million (80:20) to upgrade the Sturt Highway, between Renmark and Gawler. Extending approximately 210km, this section of Sturt Highway passes through the townships of Nuriootpa, Truro, Blanchetown, Waikerie, Barmera, Berri and Renmark.

The upgrade will improve safety, improve freight efficiency and support regional economic growth. Works may include:

  • Road rehabilitation works including shoulder sealing, resurfacing and upgraded barriers.
  • Additional overtaking lanes.
  • Improved and additional rest areas.
  • Safety enhancements at key junctions of the Sturt Highway.
  • A widened section of Highway near the Renmark caravan park to allow for movement of larger trucks.
Current Works

LocationScopeStart Date*Expected Completion
(Weather Permitting)
Latest Works Notice
Approximately 20kms east of Truro New eastbound overtaking lane August 2023 May 2024View latest works notice
Between Bower Boundary Road and Stonefield RoadPavement RehabilitationJanuary 2024Late April 2024View latest works notice
Sturt Highway/Junction Road/Airport Road Intersection Upgrade In planning             In planning

*Dates in the future are indicative

Completed Works

LocationScope Completion Date

Approximately 2kms west of Renmark

Road widening

June 2021

Between Truro and approximately 20kms west of Renmark

Shoulder sealing and apron sealing

July 2021

Old Sturt Highway/Jury Road/Fuller Road

Intersection Upgrade

May 2022

Approximately 5kms west of Truro and 3kms east of Truro

Pavement rehabilitation

July 2022

Sturt Highway/Holder Top Road

Junction upgrade

September 2022

Sturt Highway/Old Sturt Highway (east) junction

Junction upgrade

December 2022

Sturt Highway/Old Sturt Highway (west) junction

Junction upgrade

September 2022

Stockyard Plain

Upgrade to existing eastbound rest areas

December 2022

Kingston on Murray             Upgrade to exisiting eastbound and westbound rest areas March 2023
Approximately 20kms east of Waikerie             new eastbound overtaking lane March 2023
Approximately 20kms west of BlanchetownNew eastbound overtaking laneMarch 2023
Approximately 2kms northeast of Gawler and approximately 1kms northeast of NuriootpaPavement RehabilitationMay 2023
Yamba Existing westbound rest area upgrade June 2023
Shea-Oak LogNew eastbound rest areaOctober 2023
AnnadaleNew eastbound rest areaOctober 2023

Further Information

For more information, or to register for project update please: