Project Overview
The Gawler East Link Road will provide local traffic with direct access to Main North Road without travelling through the Gawler town Centre, reducing travel times, reducing the likelihood of crashes and minimising the vehicle emissions cause by travel delays.
Major works have been completed and the road is open to traffic as of 18 October 2020.
Project Concept Plan
Following an intensive review process to consolidate and consider all findings, issues and opportunities, it was determined the best outcome for the Gawler East Link Road was to follow the State Government (DIT) Alignment.
Please click here for a copy of the latest concept plan for the Gawler East Link Road Project.
Project Timeline
Project Phase | Activities | Date |
---|---|---|
Pre-construction | Contract Award | February-March 2018 |
Pre-construction | Design development | March 2018 - March 2019 |
Pre-construction | Service Relocations | September 2018 - March 2019 |
Construction | Major construction commences | November 2018 |
Construction | Major construction works complete | 3rd quarter 2020 |
Post-construction | Operation and maintenance | 3rd quarter 2020 |
Further information
If you have any further enquiries or would like to register your interest in the project, please contact the project team: