Project Overview

The Gawler East Link Road will provide local traffic with direct access to Main North Road without travelling through the Gawler town Centre, reducing travel times, reducing the likelihood of crashes and minimising the vehicle emissions cause by travel delays.

Major works have been completed and the road is open to traffic as of 18 October 2020.

Project Concept Plan

Following an intensive review process to consolidate and consider all findings, issues and opportunities, it was determined the best outcome for the Gawler East Link Road was to follow the State Government (DIT) Alignment.

Please click here for a copy of the latest concept plan for the Gawler East Link Road Project.

Project Timeline


Project PhaseActivitiesDate
Pre-constructionContract AwardFebruary-March 2018
Pre-constructionDesign developmentMarch 2018 - March 2019
Pre-constructionService RelocationsSeptember 2018 - March 2019
ConstructionMajor construction commencesNovember 2018
ConstructionMajor construction works complete3rd quarter 2020
Post-constructionOperation and maintenance3rd quarter 2020