The Grove Way Intersection Upgrades, Golden Grove

As part of the State Government’s election commitment to upgrade or investigate potential upgrades in the northern suburbs to improve safety, access and to make travel easier for all users, we have upgraded two intersections on The Grove Way in Golden Grove.

These two upgrades were funded as part of the Australian Government’s Black Spot Program which directly targets improvements on high-risk roads or roads with proven crash history.

These intersections were:

  • The Grove Way, Atlantis Drive and Aeolian Drive intersection
  • The Grove Way and The Golden Way intersection

Major works were all completed in February 2025 with some minor finishing works to be complete in March 2025.

Concept Designs

The Grove Way, Atlantis Drive and Aeolian Drive Intersection concept design

This upgrade included:

  • Upgraded signals to add in right turn arrows from Atlantis Drive and Aeolian Drive onto The Grove Way
  • Traffic signal modifications & upgrades with new phasing
  • Updated line marking to improve safety at the intersection
  • Upgrading pedestrian ramps
  • Upgraded lighting

1415961

The Grove Way and The Golden Way Intersection concept design

This upgrade included:

  • Additional right turn lane from The Grove Way to The Golden Way (west bound)
  • Traffic signal modifications & upgrades with new phasing
  • Updated line marking
  • Upgrading pedestrian ramps
  • Upgraded lighting

1415964

The Golden Way, and The Grove Shopping Centre Access Junction Pedestrian Upgrades

We also upgraded the junction of The Golden Way with The Grove Shopping Centre access, Golden Grove. This project will improve pedestrian safety, particularly for pedestrians accessing Gleeson College, Golden Grove High School and Pedare Christian College.  This project is one of eight locations identified across South Australia for upgrade as part of a broader strategy to improve road safety for all pedestrians but in particular children walking to and from school.

Works were complete in February 2025.

Further Information

If you have any questions or to provide feedback on the project, please:

You can visit the links below for the latest information and to register for project updates.