The Peregrine Mixed Use Major Development, located at 270 The Parade Kensington, will serve as the national headquarters of the Peregrine Corporation.
The proposal will meet the company's growing demand for quality office space and improved work facilities and amenities.
Authorisation dates
Construction to commence (no later) - 3 May 2024
Completion of works (no later) - 3 May 2026
Assessment stages and documentation
Stage | Release Date ▼ | Documentation |
---|---|---|
Extension of time | 22 December 2021 | |
Variation 1 - Governor's Decision | 26 April 2018 | |
Governor's Decision | 16 May 2017 | |
Assessment report by Minister | 16 May 2017 | |
Release of Response Document | 5 April 2017 | |
Release of submissions made by the public to Development Report | 27 October 2016 | |
Release of assessment document by proponent for public comment | 30 September 2016 | |
Release of revised guidelines by the Development Assessment Commission with the level of assessment reconfirmed | 26 September 2016 | |
Variation to the major development declaration | 22 September 2016 | |
Release of guidelines by Development Assessment Commission with the level of assessment determined | 10 February 2016 | |
Declaration as a major development | 26 November 2015 |