Flood resilience boost for key freight corridor

Friday 16 January 2026

Flood recovery works on the Stuart Highway at Lake Windabout are complete, strengthening the vital freight route between South Australia and the Northern Territory.

In early 2022, intense rainfall and subsequent flooding caused extensive damage to sections of the Stuart Highway, disrupting travel and the transport of essential supplies and services.

These remediation works occurred in an area approximately 150 kilometres north of Port Augusta and included raising the road level and incorporating new drainage structures to enable this 1.5-kilometre stretch of the highway to withstand and remain open during flood events.

Erosion protection was also installed to boost flood resilience, strengthening the road pavement and shoulders to help prevent washouts and delivering safer, more reliable journeys in the state’s far north.

These completed works will enable the road to return to functionality sooner in the aftermath of future flooding events, reducing the economic impact of disasters and connecting regional communities with more resilient infrastructure.

The Stuart Highway runs for almost 1000 kilometres through South Australia, linking Port Augusta to Darwin. An average 900 vehicles, including 300 heavy vehicles, travel through the area near Lake Windabout each day.

In cooler months, traffic volumes along this stretch of the highway can peak at 1300 vehicles each day, with one third of these heavy vehicles.

The project forms part of the Australian and South Australian governments’ $75 million (80:20) Flood Recovery Targeted Investment to Improve National Supply Chain Resilience program, delivered over four years.

During construction, several wide loads – some more than five metres across – safely travelled through the project site.

Careful planning and traffic management also kept competitors in the World Solar Challenge on the move when they travelled through the construction zone in late August, on their way from Darwin to Adelaide.

The remediation works supported 31 full-time jobs during construction and follow the completion of flood repairs on a 1.5-kilometre section of the Stuart Highway at Glendambo.

These works included pavement rehabilitation and sealing, excavation and upgrades to culverts, and shoulder and batter protection works.