Buildings - AS4300 - Standard Template

DISCLAIMER

These contracts have been designed for DIT's own use under the supervision of experienced professionals. While other organisations may use or reference these contracts, DIT assumes no responsibility whatsoever to any other party in any matter associated with these contracts. DIT does not represent or warrant that the use of these contracts is suitable for any non-DIT project. Any organisation seeking to use these contracts must rely on its own enquiries and bears all risks associated with the use of these contracts. By downloading any document from this site, you acknowledge and agree to DIT's Website Disclaimer

Link to Current Version
AS4300-1995 Special Conditions
Current Update:  Version V10A, April 2025

Current Contract Amendments
ClauseComments
Clause 2Clause 2 - Interpretation

New definitions added for “Arrangement”, “Declared Organisation”, “Irrelevant Factor”, “List of Outstanding Items”, and “Outstanding Items
Clause 5.8Clause 5.8 - Reduction of Security and Retention Moneys
Amended Subclause 5.8.1 and amended Subclause 5.8.2 as follows:

5.8.1 Upon the later of:

(a) the Date of Practical Completion of all of the Works under the Contract;

(b) the rectification of defects and omissions in the work under the Contract notified to the Contractor at or prior to the date of the Certificate of Practical Completion has been completed as required by the Superintendent (acting reasonably),

(c) the date on which the Contractor has given to the Superintendent all operating manuals, warranties and guarantees for the Works; and

(d) the date on which the Contractor completes all Outstanding Items as identified pursuant to clause 42.5.

the Principal’s entitlement to security and retention monies will be reduced to 1% of the Contract Sum. The Principal shall, within 14 days of the entitlement reduction, release security and retention moneys in excess of the entitlement.

5.8.2 Notwithstanding clause 5.8.1, at the Superintendent’s discretion, if, in the opinion of the Superintendent it is reasonable to further reduce the Principal’s entitlement to security and retention moneys, that entitlement shall be reduced to the amount which the Superintendent determines to be reasonable. The Principal shall, within 14 days of the Superintendent making such a determination, release security and retention moneys in excess of the entitlement.”
Clause 8.9Contractor’s Consultants changed to Contractor’s consultants (in Lower Case).
Clause 9.2Added after paragraph 4 provisions requiring all subcontracts to:

* include provisions equivalent to clause 66 (Modern Slavery), 67 (Fraud Control) and 68 (Anti-Corruption)

* Incorporate security provisions which align with those set out in clause 5 and the value of subcontractor security must not exceed a total of 3% of the subcontract sum.
clause 26.4Clause 26.4 Respectful Behaviour

Replaced clause to align with shift towards gender-based violence (previous clause addressed violence against women) and zero tolerance towards all forms of acceptable behaviours.
Clause 42.1Clause 42.1 Payment Claims, Certificates, Calculations and Time for Payment
Insert new paragraph at the end of clause 42.1:

“Add to the end of clause 42.1 add “The Principal shall not make payment for any Outstanding Items identified pursuant to clause 42.5 until such time as they are completed by the Contractor.“
Clause 42.5Clause 42.5 Final Payment Claim

Added the following to give the Superintendent more control over the final payment:

“The Superintendent may in its absolute discretion attach a List of Outstanding Items to the Certificate of Practical Completion. The List of Outstanding Items must identify all Outstanding Items which must be executed, remedied, addressed or completed by the Contractor, and the timeframes for completion of each item.  The Contractor must complete the Outstanding Items within the timeframes in the List of Outstanding Items, and otherwise, to the satisfaction of the Superintendent.”
Clause 44.2Clause 44.2 Default by the Contractor

After clause 44.2(m), added:

(n)  failing to comply in part or in whole with the requirements of subclauses 69.1 and 69.3 in relation to fraud control; or

(0) failing to comply in part or in whole with the requirements of subclauses 70.2 to 70.5 (inclusive) in relation to corruption.
Clause 52Authorities Schedule 1A
Added clause 69 and 70 to the end of the table

 Authorities Schedule 1D
Added clause 71 to the end of the table.
Clause 68Clause 68 Modern Slavery
New Clause added in relation to modern slavery
Clause 69Fraud Control
New Clause to added in relation to fraud Control.
Clause 70Anti-Corruption
New Clause added in relation to anti-corruption.
Clause 71Audit
New Clause providing the Principal with audit rights.
AnnexureItem 13
Updated to –
“3% of the Contract Sum (GST exclusive portion) to be provided as 2 separate undertakings, with values of 2% and 1% of the Contract Sum.”