Getting around during construction

Temporary speed limits and lane restrictions will be in place for works on or near roads. At times, road closures will also be needed where works cannot be safely completed with these restrictions in place.

Walking, cycling and park lands access

Access to key pathways in the Adelaide Park Lands will be maintained throughout works, but there will be some changes to access.

The east-west cycle path through Victoria Park will remain open until the end of the year. Some changes will then be needed in the new year, but access into the city will be maintained.

We will provide safe, accessible detour paths around work zones throughout the construction program and display clear signage ahead of any key changes.

For an overview of where works will occur in the eastern Park Lands, see the key work zone maps (PDF, 3.7 MB).

Planned changes to nearby roads in December 2026

This table provides an overview of key upcoming changes during December. It will be regularly updated as construction progresses.

See the map for live traffic information.

Work has been prioritised around Rundle Road/East Terrace to ensure the 2027 Adelaide Fringe is unaffected. There will be no construction activity near Fringe Corner during the 2027 Adelaide Fringe and people will be able to enjoy the festival as usual.

Local businesses in Rymill Park (Park 14), King Rodney Park (Park 15) and Victoria Park (Park 16) will remain open and accessible during construction. We encourage everyone to continue visiting and supporting them.

Where Description of traffic change

Rundle Road – between Dequetteville Terrace and East Terrace

East Terrace – between Rundle Road and the O-Bahn tunnel

  • Full closure (day and night).
  • Modified access to Rundle Street will be maintained.
  • These road closures will start from 6 December 2026. They will reopen before 10 February 2027.

Dequetteville Terrace – between Rundle Road and Wakefield Road

  • Temporary overnight traffic changes, with both directions of traffic maintained on one side of the road.
  • No changes during the day.

Bartels Road and Wakefield Road

  • Temporary lane closures will occur intermittently during the day and night.

Changes to public transport routes

Public transport plays an important role in making journeys easier and keeping traffic moving.

The O’Bahn (including the O’Bahn tunnel) will continue to operate during construction.

Any temporary changes to public transport services will be communicated in advance via Adelaide Metro.

Changes to parking, taxi and rideshare zones

During construction, parking spaces and taxi and rideshare pick-up and drop-off locations directly within work zones will be unavailable.

We are working to minimise these temporary impacts wherever possible. We encourage you to use alternative options nearby.

Parking, taxi and rideshare zones will be reinstated near Fringe Corner ahead of the Adelaide Fringe.