Elizabeth Street to Winter Terrace, Prospect, works within the rail corridor - From 25 November 2019 for approx 5 weeks
Railway Terrace Kilburn night works - From 18 November 2019 for approx. 2 weeks
Pym street to Dudley Park Station, Prospect, works within the rail corridor - From 6 November 2019 for approx 4 weeks
King Street Service Locating works, Gawler - From 6 November 2019
Port Wakefield Road to Mawson Lakes Interchange, Dry Creek - From 28 October 2019
Pym Street to Gurr Street works, Prospect - From 21 October 2019
Howard Street - SA Power Networks work - 11-15 October 2019
Eighteenth Street - SA Power Networks work - 9-14 October 2019
Sixteenth Street - SA Power Networks work - 8-11 October 2019
Para Road - SA Power Networks work - 8-10 October 2019
Anderson Walk - SA Power Networks work - 30 September-4 October 2019
Dalkeith Road - SA Power Networks work - 28-30 September 2019
Torrens Road, lane closures and survey works - 19 September 2019
Dry Creek Service locating works - September 2019
King Street and Jerningham Street, Gawler - service locating and borehole drilling works - mid to late-August 2019
Anderson Walk, Smithfield - civil and preparatory works - mid-July to mid-August 2019
Sixteenth Street, Gawler South and Ashford Street, Gawler West - civil works - late July 2019
Howard Street, Gawler - civil works and power pole installation - July 2019
Purling Avenue, Edinburgh and Kettering Road, Elizabeth South - realignment of wires and cables - late July to mid-August 2019
Dalkeith Road, Kudla - realignment of wires and cables, installation of power poles - late July to early August 2019
Eighteenth Street and Dean Street, Gawler - realignment of wires and cables - early July to early August 2019
Para Road, Evanston level crossing - realignment of wires and cables - early to mid-July 2019
William Drive, Davoren Park and Donnington Road, Elizabeth North - realignment of wires and cables - early July to early August 2019
Elizabeth South Railway Station - realignment of wires and cables - late June to mid-July 2019
Commercial Road, Salisbury Plain level crossing - realignment of wires and cables - late June to mid-July 2019
Churchill Road North and Cormack Road, Dry Creek - night work (removal of power poles, realignment of overhead wires) - 27/02/2019 into 28/02/2019